B1 MCQ – Becker

  • Creator
    Topic
  • #172285
    Anonymous
    Inactive

    Becker Question –

    Fabro, Inc. produced 1500 units of Product RX-6 last week. The inputs to the production process for product RX-6 were as follows:

    450 pounds of Material A at a cost of $1.50 per pound

    300 pounds of Material Z at a cost of $2.75 per pound

    300 labor hours at a cost of $15.00 per hour.

    What is the best productivity measure for the first-line supervisor in Fabro, Inc.’s production plant?

    A. 5.00 units per labor hour

    B. 0.33 units per dollar input

    C. 2.00 units per pound

    D. $15.00 per labor hour

    Correct answer is A.

    How???

    Thanks in advance:)

Viewing 12 replies - 1 through 12 (of 12 total)
  • Author
    Replies
  • #540069
    Peanut
    Participant

    450 pounds of Material A @ $1.50 per pound $675.00

    300 pounds of Material Z @ $2.75 per pound $825.00

    Total: $1500.00

    $1500/300 labor hours= 5

    Did you know the equation and are looking for the reason? I don't really know the reason I just totally remember this MCQ from Becker, from back in January! Don't worry, the Becker calculations are much more complex than the actual exam, I promise!

    AUD 81 (X4) Previous scores 59, 72, 72
    REG 80 (X3) Previous scores 59, 60
    FAR 75 (X2) Previous score 67
    BEC 79 (X2) Previous score 58

    #540111
    Peanut
    Participant

    450 pounds of Material A @ $1.50 per pound $675.00

    300 pounds of Material Z @ $2.75 per pound $825.00

    Total: $1500.00

    $1500/300 labor hours= 5

    Did you know the equation and are looking for the reason? I don't really know the reason I just totally remember this MCQ from Becker, from back in January! Don't worry, the Becker calculations are much more complex than the actual exam, I promise!

    AUD 81 (X4) Previous scores 59, 72, 72
    REG 80 (X3) Previous scores 59, 60
    FAR 75 (X2) Previous score 67
    BEC 79 (X2) Previous score 58

    #540071
    Anonymous
    Inactive

    I got this wrong my first time through, too.

    The question is driving at what the manager can control, in this case, productivity. The numbers don't matter here.

    A. Productivity (Volume) – how many units s/he can get his/her workers to complete per hour

    B. Spending – The manager likely doesn't control purchasing/overhead/etc.

    C. Efficiency – How much material waste there is

    D. The manager probably cannot control the cost of labor, and even if s/he could the cost of labor doesn't impact productivity.

    #540113
    Anonymous
    Inactive

    I got this wrong my first time through, too.

    The question is driving at what the manager can control, in this case, productivity. The numbers don't matter here.

    A. Productivity (Volume) – how many units s/he can get his/her workers to complete per hour

    B. Spending – The manager likely doesn't control purchasing/overhead/etc.

    C. Efficiency – How much material waste there is

    D. The manager probably cannot control the cost of labor, and even if s/he could the cost of labor doesn't impact productivity.

    #540073
    Anonymous
    Inactive

    This isn't a calculation question. It's a conceptual question. It's asking which of the choices would be the best productivity measure that the production supervisor can best control. Units/DL hour is most controllable for the production supervisor. In contrast, B, C, and D are hardly, if completely not, controllable by the production supervisor. Or, at least, I think that's how I remember the answer.

    #540115
    Anonymous
    Inactive

    This isn't a calculation question. It's a conceptual question. It's asking which of the choices would be the best productivity measure that the production supervisor can best control. Units/DL hour is most controllable for the production supervisor. In contrast, B, C, and D are hardly, if completely not, controllable by the production supervisor. Or, at least, I think that's how I remember the answer.

    #540075
    Anonymous
    Inactive

    Thank you so much!!! All the answers/responses matches with the explanations provided by Becker. I didn't see it mention in the book specifically, thus had a hard time answering it.

    Thanks! Appreciate all the help:!)

    #540117
    Anonymous
    Inactive

    Thank you so much!!! All the answers/responses matches with the explanations provided by Becker. I didn't see it mention in the book specifically, thus had a hard time answering it.

    Thanks! Appreciate all the help:!)

    #540077
    Anonymous
    Inactive

    Thank you so much!!! All the answers/responses matches with the explanations provided by Becker. I didn't see it mention in the book specifically, thus had a hard time answering it.

    Thanks! Appreciate all the help:!)

    #540119
    Anonymous
    Inactive

    Thank you so much!!! All the answers/responses matches with the explanations provided by Becker. I didn't see it mention in the book specifically, thus had a hard time answering it.

    Thanks! Appreciate all the help:!)

    #540079
    jahnesta8
    Member

    I know this is late, but I figured others might be currently looking for this question. The answer choice for B isn't even the correct calculation.

    450lb @ $1.5/lb $675

    300lb @ $2.75/lb $825

    300hrs @ $15/hr $4,500

    $6,000

    1,500 units / $6,000 = $0.25 per unit, not $0.33.

    #540120
    jahnesta8
    Member

    I know this is late, but I figured others might be currently looking for this question. The answer choice for B isn't even the correct calculation.

    450lb @ $1.5/lb $675

    300lb @ $2.75/lb $825

    300hrs @ $15/hr $4,500

    $6,000

    1,500 units / $6,000 = $0.25 per unit, not $0.33.

Viewing 12 replies - 1 through 12 (of 12 total)
  • You must be logged in to reply to this topic.