BEC Question about IRR and Positive NPV

  • Creator
    Topic
  • #186805
    Anonymous
    Inactive

    I just came across this question on the WTB and the way I’m reading it, their explanation seems to conflict with the answer they’re saying is correct. Am I just reading it wrong?

    A multiperiod project has a positive net present value. Which of the following statements is correct regarding its required rate of return?

    A. Less than the company’s weighted-average cost of capital.

    B. Less than the project’s internal rate of return.

    C. Greater than the company’s weighted-average cost of capital.

    D. Greater than the project’s internal rate of return.

    This answer (B) is correct. If the project has a positive net present value it has a return greater than the required return.

Viewing 3 replies - 1 through 3 (of 3 total)
  • Author
    Replies
  • #579468
    Anonymous
    Inactive

    It is B. Since it has a positive NPV, the companies RoR < this projects IRR. It's not a well worded question though, as it says which of the following is correct regarding its (it should say ‘the companys') required rate of return.

    #579469
    Anonymous
    Inactive

    Yeah, it definitely could be better worded. I was assuming “it's” meant the project, so I selected D as the correct answer. I've noticed quite a few Wiley questions on this new test bank that are worded pretty badly.

    #579470
    M.O.D.
    Member

    This same question is in Gleim. It may have been an AICPA question at one time.

    There are many AICPA/CMA released questions that are included in the Gleim test bank.

    BA Mathematics, UC Berkeley
    Certificates in CPA and EA preparation, College of San Mateo
    CMA I 420, II 470
    FAR 91, AUD Feb 2015 (Gleim self-study)

Viewing 3 replies - 1 through 3 (of 3 total)
  • You must be logged in to reply to this topic.