Budget based on Actual Hours Worked. Please Help

  • Creator
    Topic
  • #189977
    Hammer
    Participant

    Why is the 100,000 hours used as the “budget based on actual hours” in this question? Why wouldn’t it be 94,000 x $5?

    Water Control, Inc. manufactures water pumps and uses a standard cost system. The standard factory overhead costs per water pump are based on direct labor hours and are shown below:

    Variable overhead (4 hours at $8/hour) $ 32

    Fixed overhead (4 hours at $5*/hour) 20

    Total overhead cost per unit $ 52

    *Based on a capacity of 100,000 direct labor hours per month.

    The following additional information is available for the month of November.

    22,000 pumps were produced although 25,000 had been scheduled for production.

    94,000 direct labor hours were worked at a total cost of $940,000.

    The standard direct labor rate is $9 per hour.

    The standard direct labor time per unit is four hours.

    Variable overhead costs were $740,000.

    Fixed overhead costs were $540,000.

    The fixed overhead spending variance for November was:

    FAR - 70, 81
    AUD - 83
    BEC - 77
    REG - 70, 78

    Licensed in Ohio.

    Now what the hell do I do?

Viewing 1 replies (of 1 total)
  • Author
    Replies
  • #617830
    mla1169
    Participant

    Budgets are created long before the actual hours are known. The * that you are asking about says budget based on capacity of 100,000 hours. The capacity is not the actual hours either, it is the number of hours that would be worked at full force. Further that * is only related to fixed costs which are going to be the same whether it's 100k hours, 94k hours or 1 hour. So the variance comes from the fact that only 5 x 94,000 was applied but 540k was incurred

    FAR- 77
    AUD -49, 71, 84
    REG -56,75!
    BEC -75

    Massachusetts CPA (non reporting) since 3/12.

Viewing 1 replies (of 1 total)
  • You must be logged in to reply to this topic.