VOH Efficiency Variance Question!! Help!!!

  • Creator
    Topic
  • #1590992
    AMERICANDREAM
    Participant

    A company uses a standard costing system. The production budget for year 1 was based on 200,000 units of output. Each unit requires two standard hours of manufacturing labor for completion. Total overhead was budgeted at 900K for the year, and the budgeted Fixed OH rate was $1.50 per direct manufacturing labor hour. Both variable and fixed overheads are allocated to the product based on direct manufacturing labor hours. The actual data for year 1 are as follows:

    Actual Production in units = 198,000
    Actual Direct Manufacturing Labor hours = 425,000
    Actual Variable OH = 352,000
    Actual Fixed OH = 575,000

    ————————————————————————
    The way I approached this problem was:

    Actual VOH — price var.— Flexible VOH — eff. var.— Budgeted VOH
    352k………………………..297k………………………….300k

    Where:
    352k = given
    297k = input*Actual Quantity*Standard rate = 2*198k*0.75
    300k = 900k – 600k
    0.75 is from 300k/400k

    My answer (favorable of 3k) is not one of the answer options. What am I doing wrong here? I don’t understand looking at the explanation 🙁

    AUD - 92
    BEC - NINJA in Training
    FAR - 90
    REG - 88
    If you think you failed, you passed.
Viewing 1 replies (of 1 total)
  • Author
    Replies
  • #1590993
    Fk
    Participant

    @AmericanDream

    Budgeted output = 200,000 x 2 Labour hours = 400,000 Labour hours

    Budgeted fixed overhead = 400.000 LH x $ 1.50 = $ 600,0000

    Total Budgeted Overhead = $ 900,000
    Less : Budgeted FOH = $ 600,000
    300,000 Budgeted Variable Overhead

    Budgeted Variable Overhead = 300,000/400000 = 0.75

    SQ * = Actual Output x SQ = 198,000 X 2 = 396000

    ( AQ – SQ*) SP
    ( 425,000 – 396000 ) .75
    21,750 U

    Fk
Viewing 1 replies (of 1 total)
  • You must be logged in to reply to this topic.