Calculation of Manufacturing Cycle Efficiency ???

  • Creator
    Topic
  • #200920
    kukuna2008
    Participant

    A Ninja MCQ said: From order being placed to start of production is 10 days, from start of production to completion is 5 days, Inspection time is 1.5 days, Process time is 3 days, and Move time is 2.5 days. so what is the Manufacturing Cycle Efficiency ratio?

    the answer is 3 / (5+1.5+3+2.5) = 25%

    I thought the answer should be 5 / (5+1.5+3+2.5) = 41.7% the production days of 5 should be the value added time, can anyone tell me why does not use it? Thank you!